Noise
Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(Restricted Hours - 2300-0700 on all
days) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location CM1 - Nga Lai House, Yau Lai Estate Phase
1, Yau Tong |
|
|
|
|
Date |
Time |
Weather |
dB (A) (5-min) |
Baseline Level |
Construction Noise
Level |
|
|
|
|
L eq |
L10 |
L 90 |
Average Leq |
L eq |
L eq |
|
|
|
|
14-Jun-19 |
23:00 |
Cloudy |
62.3 |
63.7 |
59.1 |
62.1 |
63.7 |
62Measured ¡Ø Baseline |
|
|
|
|
23:05 |
62.1 |
63.6 |
59.0 |
|
|
|
|
23:10 |
62.0 |
63.9 |
58.9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location CM2 - Bik Lai House, Yau Lai Estate Phase
1, Yau Tong |
|
|
|
|
Date |
Time |
Weather |
dB (A) (5-min) |
Baseline Level |
Construction Noise
Level |
|
|
|
|
L eq |
L10 |
L 90 |
Average Leq |
L eq |
L eq |
|
|
|
|
14-Jun-19 |
23:20 |
Cloudy |
61.5 |
63.9 |
58.5 |
61.3 |
61.2 |
45 |
|
|
|
|
23:25 |
61.0 |
64.0 |
58.7 |
|
|
|
|
23:30 |
61.3 |
63.8 |
58.6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location CM3 - Block S, Yau Lai Estate Phase 5, Yau
Tong |
|
|
|
|
Date |
Time |
Weather |
dB (A) (5-min) |
Baseline Level |
Construction Noise
Level |
|
|
|
|
L eq |
L10 |
L 90 |
Average Leq |
L eq |
L eq |
|
|
|
|
14-Jun-19 |
23:40 |
Cloudy |
58.7 |
61.9 |
57.2 |
58.9 |
62.9 |
59Measured ¡Ø Baseline |
|
|
|
|
23:45 |
59.0 |
62.1 |
57.0 |
|
|
|
|
23:50 |
58.9 |
61.7 |
57.0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Remark: The exceedanes of
night time noise limit level (55dB(A)) were not due to the Project but the
road traffic near Eastern Harbour Crossing tunnel. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|