Environmental
Monitoring Works
Key Information
in the Reporting Month
Key Construction
Work in the reporting month & the next reporting month
Construction
Activities undertaken during the Reporting Month
Status of Environmental Licences,
Notification and Permits
Monitoring
Parameters and Frequency
Monitoring Methodology and QA/QC Procedure
Monitoring Parameters and Frequency
Sampling Management and Supervision
Post-Translocation Coral Monitoring
Alert, Alarm and Action Levels
Mitigation Measures for Cultural Heritage
8. LANDSCAPE AND VISUAL IMPACT REQUIREMENTS
Monitoring Parameters and Frequency
Implementation Status of Environmental
Mitigation Measures
12. ENVIRONMENTAL NON-CONFORMANCE
Summary of Environmental Non-Compliance
Summary of Environmental Complaint
Summary of Environmental Summon and
Successful Prosecution
Key Issues for the Coming Month
14. CONCLUSIONS AND RECOMMENDATIONS
lIST OF TABLES
Table I Non-compliance
(exceedance) Recorded for the Project in the Reporting Month
Table II Key
Information in the Reporting Month
Table III Summary
Table for Complaint Details in the Reporting Month
Table IV Summary
Table for Key Construction Work in the Reporting Month
Table V Summary Table for
Site Activities in the next Reporting Period
Table 2.1 Key
Project Contacts
Table 2.2 Summary
Table for Major Site Activities in the Reporting Month
Table 2.4 Summary of the Status of Environmental Licences,
Notification and Permits
Table 3.1 Locations
for Air Quality Monitoring
Table 3.2 Air
Quality Monitoring Equipment
Table 3.3 Impact
Dust Monitoring Parameters, Frequency and Duration
Table 3.4 Major
Dust Source during Air Quality Monitoring
Table 4.1 Noise
Monitoring Stations
Table 4.2 Noise
Monitoring Equipment
Table 4.3 Noise
Monitoring Parameters, Frequency and Duration
Table 4.4 Major
Noise Source during Noise Monitoring
Table 4.5 Baseline
Noise Level and Noise Limit Level for Monitoring Stations
Table 4.7 Baseline
Noise Level and Noise Limit Level for Monitoring Stations (Night-time)
Table 5.1 Not Used
Table 5.2 Marine
Water Quality Monitoring Stations
Table 5.3 Water
Quality Monitoring Equipment
Table 5.4 Water
Quality Monitoring Parameters and Frequency
Table 5.5 Methods
for Laboratory Analysis for Water Samples
Table 5.6 Summary
of Groundwater Quality Monitoring Results
Table 7.1 Cultural
Heritage Monitoring Equipment
Table 7.2 AAA
Levels for Monitoring for Cultural Heritage
Table 9.1 Landfill Gas Monitoring Equipment
Table 13.1 Summary
Table for Site Activities in the next Reporting Period
lIST OF
FIGUREs
Figure 1a Site Portions
under Works Contract No. NE/2015/01 (Lam Tin Side)
Figure 1b Site Portions
under Works Contract No. NE/2015/01 (Tseung Kwan O Side)
Figure 1c Site Portions
under Works Contract No. NE/2015/02
Figure 1d Site Portions
under Works Contract No. NE/2015/03
Figure 1e Site Portions
under Works Contract No. NE/2017/01
Figure 1f Site Portions
under Works Contract No. NE/2017/01
Figure 1g Site Portions
under Works Contract No. NE/2017/02
Figure 1h Site Portions
under Works Contract No. NE/2017/02
Figure 2 Locations of
Air Quality Monitoring Stations
Figure 3 Locations of
Construction Noise Monitoring Stations
Figure 4 Not Used
Figure 5 Locations of
Marine Water Quality Monitoring Stations
Figure 6 Locations of
Landfill Gas Monitoring
Figure 7 Location of
Post-translocation Coral Monitoring
Figure 8 Location of Monitoring for Cultural Heritage
Figure 9 Not Used
lIST OF APPENDIces
Appendix A
Action and Limit Levels
Appendix
B
Copies of Calibration Certificates
Appendix C
Weather Information
Appendix D
Environmental Monitoring Schedules
Appendix E
1-hour TSP Monitoring Results and Graphical Presentations
Appendix F
24-hour TSP Monitoring Results and Graphical Presentations
Appendix G
Noise Monitoring Results and Graphical Presentations
Appendix H Not Used
Appendix I
Marine Water Quality Monitoring Results and
Graphical Presentations
Appendix J Not Used
Appendix K
Summary of Exceedance
Appendix L
Site Audit Summary
Appendix M Event and Action Plans
Appendix N Implementation Schedule And Recommended Mitigation Measures
Appendix O Summaries of Environmental Complaint, Warning, Summon and
Notification of Successful Prosecution
Appendix P
Waste Generation in the Reporting Month
Appendix Q Tentative Construction Programme
Appendix R Record of Landfill Gas Monitoring by Contractor
Appendix S Not Used
Appendix
T
Cultural Heritage Monitoring Results
Appendix U Piezometer Monitoring Results
Appendix V Updated Surface Runoff Management Plan
1. This is the 43th Environmental
Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited
for the “Agreement No. CE 59/2015 (EP) Environmental Team for Tseung Kwan O –
Lam Tin Tunnel – Design and Construction” (hereinafter called “the Project”). This report documents the findings of
EM&A Works conducted in May 2020.
2. During the reporting month, the
following works contracts were undertaken:
· Contract No. NE/2015/01 – Tseung
Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works;
· Contract No. NE/2015/02 – Tseung
Kwan O – Lam Tin Tunnel – Road P2 and Associated Works;
· Contract No. NE/2015/03 – Tseung Kwan O – Lam
Tin Tunnel – Northern Footbridge;
· Contract No. NE/2017/01 – Tseung Kwan O – Lam
Tin Tunnel –Tseung Kwan O Interchange and Associated Works
· Contract No. NE/2017/02 – Tseung Kwan O – Lam
Tin Tunnel – Road P2/D4 and Associated Works.
· Contract No. NE/2017/06 – Tseung
Kwan O – Lam Tin Tunnel – Traffic Control and Surveillance System(TCSS) and
Associated Works
· Contract No. NE/2017/07 – Cross Bay
Link, Tseung Kwan O – Main Bridge and Associated Works.
3. Environmental monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed. Site Inspections/Audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.
4. Summary of the non-compliance
(exceedance) in the reporting month for the Project is tabulated in Table I.
Table I Non-compliance (exceedance) Record for the Project in the Reporting Month
Environmental Monitoring |
No. of Non-compliance (Exceedance) |
No. of Non-compliance (Exceedance) due to Construction Activities of this Project |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
Air Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
3 |
1 |
2 |
0 |
Refer to Appendix K & O |
Marine Water Quality |
39 |
95 |
0 |
0 |
Refer to Appendix K |
Groundwater Level Monitoring
(Piezometer Monitoring) |
0 |
N/A1 |
0 |
N/A1 |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
0 |
0 |
0 |
0 |
N/A |
Landfill Gas |
0 |
0 |
0 |
0 |
N/A |
Note:(1) No Limit Level for Groundwater Level Monitoring (Piezometer
Monitoring).
Air Quality Monitoring
5. No Action/Limit Level exceedance
for 1-hour TSP monitoring was recorded.
6. No Action/Limit Level exceedance
for 24-hour TSP monitoring was recorded.
Construction Noise Monitoring
7. Three (3) Action Level exceedances
were recorded due to the documented complaints received in this reporting
month. The Summary of Documented Complaints in Reporting Month is tabulated in
Table III.
8. One (1) Limit Level exceedance for
day time and no limit level exceedance for night time construction noise monitoring
were recorded in the reporting month.
Water Quality Monitoring
9. Groundwater quality monitoring had been suspended since October 2019 upon the agreement by EPD. Further details should be founded at Section 5.1.
10. All marine water quality monitoring was conducted as scheduled in the reporting month. There were thirty-nine (39) Action Level and ninety-five (95) Limit Level exceedances in Monitoring Stations (M) during marine water quality monitoring. During this reporting month, no sand plume was observed during the water quality monitoring and site audits, therefore there is no direct evidence that the recent exceedances were due to the construction works of the Project. Details of this investigation are presented in Section 5. Daily silt curtain inspection and weekly diving inspection have been carried out by contractor, the record, as reviewed by the site auditors, indicated that silt curtains were found in good conditions.
11. Construction phase daily piezometer
monitoring by the Contractor commenced in June 2018. It has switched to monthly
basis since 3 October
2018 as the construction activity was 120m away from the piezometer gate. The
daily piezometer monitoring has resumed on 19 November 2018, as the
construction activity was within 50m. No Action Level exceedance was recorded
in the reporting month.
Ecological Monitoring
12. Post-translation coral monitoring
survey shall be conducted once every 3 months for a period of 12 months after
completion of coral translocation. The post-translocation coral monitoring
surveys were completed in November 2017.
Monitoring on Cultural Heritage
13. Monitoring of impacts on Cultural
Heritage at Cha Kwo Ling Tin Hau Temple commenced in May 2017. No Alert, Alarm and Action (AAA) Level exceedance
was recorded in the reporting month.
Landscape and Visual Monitoring and
Audit
14. The implementation of landscape and
visual mitigation measures was checked during the environmental site
inspections. Recommended follow-up actions have been discharged by the
Contractor. Details of the audit
findings and implementation status are presented in Section 10.
Landfill Gas Monitoring
15. Monitoring of landfill gases
commenced in December 2016 and were
carried out by the Contractor at excavation
location, Portion III. No Limit Level
exceedance was recorded.
Environmental Site Inspection
16. Joint weekly site inspections were
conducted by representatives of the Contractor, Engineer and Environmental
Team. The representative of the IEC joined the site inspection for NE/2015/01,
NE/2015/02, NE/2017/01 and NE/2017/02 on 22, 23, 23 and 23 April 2020
respectively. Details of the audit findings and implementation status are
presented in Section 10.
Waste Management
17.
Wastes generated from this
Project include inert construction and demolition (C&D) materials,
non-inert C&D materials and marine sediment. Details of waste management
data is presented in Section 11 and Appendix P.
18. Summary of key information in the
reporting month is tabulated in Table II
Table II Key Information in the Reporting Month
Monthly Complaints |
Event Details |
Action Taken |
Status |
|
Number |
Nature |
|||
|
|
|
|
|
May 2020 |
4 |
Air / Noise |
Details refer to App O |
Draft CIRs submitted/ On-going |
April 2020 |
43 |
Air / Noise / Light / Odour |
Details refer to App O |
Draft CIRs submitted/ Closed |
March 2020 |
11 |
Noise / Odour / Water |
Details refer to App O |
Draft CIRs submitted/ Closed |
February 2020 |
4 |
Noise |
Details refer to App O |
Closed |
January 2020 |
61 |
Noise |
Details refer to App O |
Closed |
December 2019 |
5 |
Noise |
Details refer to App O |
Closed |
Notifications of any summons
& prosecutions received |
0 |
--- |
N/A |
N/A |
1. One new complaint was received
after the submission of the EMA Report (Jan 2020) 2. 1 of the complaint in April
2020 was missed out and discovered at mid-May 2020. |
19. Summary of complaints received in the
reporting month is tabulated in Table
III.
Table III Summary
of Complaints Details in Reporting Month
Complaint |
Investigation Findings |
Follow-up Action / Mitigation Measure |
Tseung Kwan O Side |
||
Odour nuisance nearby TKO MTR Station |
Investigation
undergoing |
|
Noise nuisance at Noght and Air Quality Impact from Works |
||
Continuous diesel fuel odor nuisance near Park Central |
No direct evidence showed that the odour originated from the
work sites of TKO-LTT. The complaint is considered non-valid and details
shall be referred to CIR-A16 |
NIL |
Noise generated in early mornings of early May |
Investigation
undergoing |
|
Noise nuisance from Tunnel Works |
20. Summary of key construction work in
the reporting month is tabulated in Table
IV.
Table IV Summary Table for Key
Construction Work in the Reporting Month
Contract No. |
Project Title |
Site Activities (May 2020) |
|
NE/2015/01 |
Tseung Kwan O
– Lam Tin Tunnel – Main Tunnel and Associated Works |
Lam Tin Interchange |
1) EHC2 U-Trough 2) Site Formation – Area 1G1, Area
1G2, Area 2, Area 3, Area 4 & Area
5 3) Administration Building |
Main Tunnel |
4) Main Tunnel Excavation 5) Main Tunnel Lining Works |
||
TKO Interchange |
6) Haul Road Construction and Site
Formation & Slope Works 7) Bridge Construction 8) East Ventilation Building |
||
NE/2015/02 |
Tseung Kwan O – Lam Tin
Tunnel – Road P2 and Associated Works |
1)
Site formation works, road and drainage for Road P2 CH500-CH650 and
SR1 2)
R.C. Structure works for U-trough CH318 – CH363.50 3)
Construction of utility trough and pre-cast concrete barrier at P2
U-trough CH411 – CH500 and SR2 CH170 – CH250 4)
Installation of socketed H-pile at S200 CH821 – P2 CH105 5)
Pre-boring for sheetpile at S200 CH821 – P2 CH105 6)
Pre-boring for sheetpile at storm water manhole 9101 – 9103 7)
Sloping seawall construction 8)
Removal of temporary cofferdam 9)
Construction of directional sign footing DS25, ADS22 10) Sheetpile installation at S200
CH821-P2 CH105 11) Installation of socketed H-pile
at CT01 CH117 – CH336 12) TAM grouting works at
CH105-CH318 cofferdamExcavation for abutment 13) Trimming of bored-pile heads 15) Construction of barrier at
CH500 – CH650 16) Drainage works at SR1 footpath
/ cycle truck 17) Installation of ELS at
cofferdam CH105 – CH318 18) Excavation of 3rd
layer of ELS at CH105 – CH318 cofferdam 19) Backfilling works for
reinstatement of Tong Yin Street 20) Construction of storm water
drain system for SHH 9101 – 9103 |
|
NE/2015/03 |
Tseung Kwan O – Lam Tin Tunnel – Northern Footbridge |
The construction works under the
contract had been completed in December 2019. The EM&A works were
terminated in late April 2020. |
|
NE/2017/01 |
Tseung Kwan O – Lam Tin Tunnel – Tseung Kwan O Interchange and
Associated Works |
1) Construction of Pier 2) Construction of Pier Head Works 3) Bored Piling Works 4) Segment Erection Works |
|
NE/2017/02 |
Tseung Kwan O
– Lam Tin Tunnel – Road P2/D4 and Associated Works |
1) Inspection pit excavation and
utility diversion works 2) Construction of drainage and
watermain 3) Pile cap 4) Asphalt Paving 5) Pier, Staircase and Lift Shalt
Construction 6) Road Works |
|
NE/2017/06 |
Tseung Kwan O – Lam Tin Tunnel – Traffic Control and Surveillance
System(TCSS) and Associated Works |
Nil |
21. The future key environmental issues
in the coming month include:
Table V Summary Table for Site Activities in the
next Reporting Period
Contract No. and Project Title |
Site Activities (June 2020) |
Key Environmental Issues * |
|
NE/2015/01 - Tseung Kwan O – Lam
Tin Tunnel – Main Tunnel and Associated Works |
Lam Tin Interchange |
1) EHC2 U-Trough 2) Site Formation – Area 1G1, Area
1G2, Area 2, Area 3, Area 4 & Area 5 3) Administration Building |
(A) / (B) / (C) / (D) / (E) / (G) |
Main Tunnel |
4) Main Tunnel Excavation 5) Main Tunnel Lining Works |
(B) |
|
TKO Interchange |
6) Haul Road Construction and Site
Formation & Slope Works 7) Bridge Construction 8) East Ventilation Building |
(A) / (C) / (D) / (E) / (F) / (I) |
|
NE/2015/02 - Tseung Kwan O – Lam
Tin Tunnel – Road P2 and Associated Works |
1) Site formation works, road and
drainage for Road P2 CH500-CH650 and SR1 2) R.C. Structure works for
U-trough CH318 – CH363.50 3) Construction of utility trough
and pre-cast concrete barrier at P2 U-trough CH411 – CH500 and SR2 CH170 –
CH250 4) Installation of socketed H-pile
at S200 CH821 – P2 CH105 5) Pre-boring for sheetpile at
S200 CH821 – P2 CH105 6) Pre-boring for sheetpile at
storm water manhole 9101 – 9103 7) Sloping seawall construction 8) Removal of temporary cofferdam 9) Construction of directional
sign footing DS25, ADS22 10) Sheetpile installation at S200
CH821-P2 CH105 11) Installation of socketed H-pile
at CT01 CH117 – CH336 12) TAM grouting works at
CH105-CH318 cofferdamExcavation for abutment 13) Trimming of bored-pile heads 14) Construction of abutment 15) Construction of barrier at
CH500 – CH650 16) Drainage works at SR1 footpath
/ cycle truck 17) Installation of ELS at
cofferdam CH105 – CH318 18) Excavation of 3rd
layer of ELS at CH105 – CH318 cofferdam 19) Backfilling works for
reinstatement of Tong Yin Street 20) Construction of storm water
drain system for SHH 9101 – 9103 |
(A) / (B) / (C) / (D) / (E) / (G)
/ (I) |
|
NE/2015/03 - Tseung Kwan O – Lam
Tin Tunnel – Northern Footbridge |
The construction works under the contract had been completed in December
2019. Materials are being removed from works area. |
N/A |
|
NE/2017/01 – Tseung Kwan O
Interchange and Associated Works |
1) Dismantling
of Temporary Working Platforms 2) Bored
Piling Works 3) Installation
of Precast Pile Cap Shell 4) Construction of Pile Cap 5) Construction of Pier 6) Construction of Pier Head works 7) Segment erection works 8) Construction of Bridge Decks |
(A) / (B) / (E) / (F) / (G) |
|
NE/2017/02 –Tseung Kwan O - Lam
Tin Tunnel - Road P2/D4 and Associated Works |
1) Inspection pit excavation and
utility diversion works 2) Construction of drainage and
watermain 3) Pile cap 4) Pre-bored Socket-H Pile 5) Asphalt Paving 6) Pier, Staircase and Lift Shalt
Construction 7) Road Works |
(A) / (B) / (E) / (F) / (G) |
|
NE/2017/06 – Tseung Kwan O – Lam
Tin Tunnel – Traffic Control and Surveillance System(TCSS) and Associated
Works |
Nil |
N/A |
Note:
(A) Watering for dust generation from
haul road, stockpiles of dusty materials, exposed site area, excavation works
and rock breaking activities;
(B) Noisy construction activity such as
rock-breaking activities and piling works;
(C) Runoff from exposed slope or site
area;
(D) Wastewater and runoff discharge
from site;
(E) Accumulation of silt, mud and sand
along U-channels and sedimentation tanks;
(F) Set up and implementation of temporary
drainage system for the surface runoff;
(G) Storage of chemicals/fuel and
chemical waste/waste oil on site;
(H) Accumulation and storage of general
and construction waste on site; and
(I)
Marine
water quality impact and indirect
impact to coral communities due to marine construction for TKO-LTT reclamation
1.1
Cinotech
Consultants Limited (Cinotech) was commissioned by Civil Engineering and Development Department
(CEDD) as the Environmental Team (ET) to undertake environmental monitoring
and auditing services for the Works Contracts involved in the implementation of
Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) project to ensure that the environmental performance of the Works
Contracts comply with the requirements specified in the Environmental Permit
(EP), Environmental Monitoring & Audit (EM&A) Manual, Environmental
Impact Assessment (EIA) Report of the TKO-LTT project and other relevant
statutory requirements. This is the 43th
Monthly EM&A report summarizing the EM&A works for the Project in May 2020.
1.2
This
is the 43th Monthly EM&A Report which summarises the impact
monitoring results and audit findings for the EM&A programme during the
reporting period in May 2020.
1.3
The
structure of the report is as follows:
Section 1: Introduction – purpose and structure of the report.
Section 2: Contract Information
– summarises background and scope of the Contract, site description, project
organization and contact details, construction programme, the construction
works undertaken and the status of Environmental Permits/Licenses during the
reporting month.
Section 3: Air Quality Monitoring
– summarises the monitoring parameters, monitoring programmes, monitoring
methodologies, monitoring frequency, monitoring locations, Action and Limit
Levels, monitoring results and Event / Action Plans.
Section 4: Noise Monitoring –
summarises the monitoring parameters, monitoring programmes, monitoring
methodologies, monitoring frequency, monitoring locations, Action and Limit
Levels, monitoring results and Event / Action Plans.
Section 5: Water Quality
Monitoring – summarises the monitoring parameters, monitoring programmes,
monitoring methodologies, monitoring frequency, monitoring locations, Action
and Limit Levels, monitoring results and Event / Action Plans.
Section 6: Ecological Monitoring
– summarises the monitoring parameters, monitoring programmes, monitoring
methodologies, monitoring frequency, monitoring locations and Action and Limit Levels,
monitoring results and Event / Action Plans.
Section 7: Cultural Heritage
–summarises the monitoring parameters, monitoring programmes, monitoring
methodologies, monitoring frequency, monitoring locations and monitoring
results.
Section 8: Landscape and Visual
Monitoring Requirements – summarises the requirements of landscape and
visual monitoring
Section 9: Landfill Gas
Monitoring – summarises the monitoring parameters, monitoring programmes,
monitoring methodologies, monitoring frequency, monitoring locations,
monitoring results and Limit Levels and Action Plan
Section 10: Environmental Site
Inspection – summarises the audit findings of the weekly site inspections
undertaken within the reporting month.
Section 11: Waste Management
– summarises the waste management data in the reporting month.
Section 12: Environmental
Non-conformance – summarises any monitoring exceedance, environmental
complaints, environmental summons and successful prosecutions within the
reporting month.
Section 13: Future Key Issues
– summarises the impact forecast and monitoring schedule for the next three
months.
Section 14: Conclusions and
Recommendation
2.1
In 2002, Civil Engineering and Development Department (CEDD)
commissioned an integrated planning and engineering study under Agreement No.
CE 87/2001 (CE) “Further Development of Tseung Kwan O – Feasibility Study” (the
“TKO Study”) to formulate a comprehensive plan for further development of TKO
New Town. It recommended to further
develop TKO to house a total population of 450,000 besides the district’s
continuous commercial and industrial developments.
2.2
At present, the Tseung Kwan O Tunnel is the main connection between
Tseung Kwan O (TKO) and other areas in the territory. To cope with the anticipated transport need,
the TKO Study recommended the provision of Tseung Kwan O – Lam Tin Tunnel
(TKO-LTT) (hereinafter referred to as “the Project”) and Cross Bay Link (CBL)
to meet the long-term traffic demand between TKO and the external areas. The
site layout plan for the Project is shown in Figure 1. CBL was also entrusted with part of the marine viaducts
near Tseung Kwan O Interchange since the commencement of the CBL project the
December 2018.
2.3
The Environmental
Impact Assessment (EIA) Report for the TKO-LTT project was approved under the
Environmental Impact Assessment Ordinance (EIAO) in July 2013. The
corresponding Environmental Permit (EP) was issued in August 2013 (EP no.:
EP-458/2013). Variations to the EP was applied and the latest EP (EP no.:
EP-458/2013/C) was issued by the Director of Environmental Protection (DEP) in
January 2017.
2.4
The commencement dates
of construction of this Project are:
Contract No. NE/2015/01 and Contract No. NE/2015/02: 7
November 2016.
Contract No. NE/2015/03: 29 May 2017.
Contract No. NE/2017/02: 15 March 2018.
Contract No. NE/2017/01: 23 May 2018.
Contract No. NE/2017/06: 09 November 2018.
2.5
Different parties with
different levels of involvement in the project organization include:
·
Project
Proponent – Civil Engineering and Development Department (CEDD)
·
The
Engineer and the Engineer’s Representative (ER) – AECOM
·
Environmental
Team (ET) – Cinotech Consultants Limited (Cinotech)
·
Independent
Environmental Checker (IEC) – AnewR Consulting Limited (AnewR)
2.6
The key contacts of
the Project are shown in Table 2.1.
Table 2.1 Key Project Contacts
Role |
Contact Person |
Phone No. |
Fax No. |
|
CEDD |
Project Proponent |
Mr. LO Sai Pak,
Sunny |
2301 1384 |
2739 0076 |
AECOM |
Engineer’s Representative |
Mr. KY Chan |
3922 9000 |
2759 1698 |
Cinotech |
Environmental Team |
Dr. HF Chan |
2151 2088 |
3107 1388 |
Mr. KS Lee |
2151 2091 |
|||
AnewR |
Independent Environmental Checker |
Mr. Adi Lee |
2618 2836 |
3007 8648 |
2.7
The major site activities undertaken in the reporting month included:
Table 2.2 Summary Table for Major Site Activities in
the Reporting Month
Contract No. |
Project Title |
Site Activities ( |