Environmental
Monitoring Works
Key
Information in the Reporting Month
Key
Construction Work in the reporting month & the next reporting month
Construction
Activities undertaken during the Reporting Month
Status of Environmental Licences,
Notification and Permits
Monitoring
Parameters and Frequency
Monitoring Methodology and QA/QC
Procedure
Monitoring Parameters and Frequency
Sampling Management and Supervision
Post-Translocation Coral Monitoring
Alert, Alarm and Action Levels
Mitigation
Measures for Cultural Heritage
8. LANDSCAPE AND VISUAL IMPACT
REQUIREMENTS
Monitoring Parameters and Frequency
Monitoring Equipment noise mitigation
Implementation Status of
Environmental Mitigation Measures
12. ENVIRONMENTAL NON-CONFORMANCE
Summary of Environmental Complaint
Summary of Environmental Summon and
Successful Prosecution
Key Issues for the Coming Month
14. CONCLUSIONS AND RECOMMENDATIONS
lIST
OF TABLES
Table I Non-compliance (exceedance) Recorded for the Project in the Reporting Month
Table II Key Information in the Reporting Month
Table III Summary Table for Complaint Details in the Reporting Month
Table IV Summary Table for Key Construction Work in the Reporting Month
Table V Summary Table for Site Activities in the next Reporting Period
Table 2.1 Key Project Contacts
Table 2.2 Summary Table for Major Site Activities in the Reporting Month
Table
2.4 Summary of the Status of
Environmental Licences, Notification and Permits
Table 3.1 Locations for Air Quality Monitoring
Table 3.2 Air Quality Monitoring Equipment
Table 3.3 Impact Dust Monitoring Parameters, Frequency and Duration
Table 3.4 Major Dust Source during Air Quality Monitoring
Table 4.1 Noise Monitoring Stations
Table 4.2 Noise Monitoring Equipment
Table 4.3 Noise Monitoring Parameters, Frequency and Duration
Table 4.4 Major Noise Source during Noise Monitoring
Table 4.5 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Table 4.7 Baseline Noise Level and Noise Limit Level for Monitoring Stations (Night-time)
Table 5.1 Not Used
Table 5.2 Marine Water Quality Monitoring Stations
Table 5.3 Water Quality Monitoring Equipment
Table 5.4 Water Quality Monitoring Parameters and Frequency
Table 5.5 Methods for Laboratory Analysis for Water Samples
Table 5.6 Not Used
Table
7.1 Cultural Heritage Monitoring
Equipment
Table 7.2 AAA Levels for Monitoring for Cultural Heritage
Table 9.1 Landfill Gas Monitoring Equipment
Table 13.1 Summary Table for Site Activities in the next Reporting Period
lIST OF FIGUREs
Figure
1a Site Portions under Works
Contract No. NE/2015/01 (Lam Tin Side)
Figure
1b Site Portions under Works
Contract No. NE/2015/01 (Tseung Kwan O Side)
Figure
1c Site Portions under Works
Contract No. NE/2015/02
Figure
1d Site Portions under Works
Contract No. NE/2015/03
Figure
1e Site Portions under Works
Contract No. NE/2017/01
Figure
1f Site Portions under Works
Contract No. NE/2017/01
Figure
1g Site Portions under Works
Contract No. NE/2017/02
Figure
1h Site Portions under Works
Contract No. NE/2017/02
Figure
2 Locations of Air Quality
Monitoring Stations
Figure
3 Locations of Construction
Noise Monitoring Stations
Figure 4 Not Used
Figure
5 Locations of Marine Water
Quality Monitoring Stations
Figure
6 Locations of Landfill Gas
Monitoring
Figure
7 Location of Post-translocation
Coral Monitoring
Figure
8 Location of Monitoring for Cultural Heritage
Figure 9 Not Used
lIST OF APPENDIces
Appendix
A
Action
and Limit Levels
Appendix
B
Copies
of Calibration Certificates
Appendix
C
Weather Information
Appendix D
Environmental
Monitoring Schedules
Appendix E
1-hour
TSP Monitoring Results and Graphical Presentations
Appendix F
24-hour
TSP Monitoring Results and Graphical Presentations
Appendix G
Noise
Monitoring Results and Graphical Presentations
Appendix
H
Not Used
Appendix I
Marine
Water Quality Monitoring Results and Graphical Presentations
Appendix J Not Used
Appendix K
Summary
of Exceedance
Appendix L Site Audit Summary
Appendix M
Event and Action Plans
Appendix N
Implementation
Schedule And Recommended Mitigation Measures
Appendix O
Summaries
of Environmental Complaint, Warning, Summon and Notification of Successful
Prosecution
Appendix P
Waste
Generation in the Reporting Month
Appendix Q
Tentative
Construction Programme
Appendix R
Record
of Landfill Gas Monitoring by Contractor
Appendix
S
Updated Drainage Plan
(NE2015/02)
Appendix T
Cultural Heritage Monitoring Results
Appendix
U
Not Used
Appendix V Surface
Runoff Management Plan
1. This is the 54th Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the “Agreement No. CE 59/2015 (EP) Environmental Team for Tseung Kwan O – Lam Tin Tunnel – Design and Construction” (hereinafter called “the Project”). This report documents the findings of EM&A Works conducted in April 2021.
2. During the reporting month, the following works contracts were undertaken:
· Contract No. NE/2015/01 – Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works;
· Contract No. NE/2015/02 – Tseung Kwan O – Lam Tin Tunnel – Road P2 and Associated Works;
· Contract No. NE/2015/03 – Tseung Kwan O – Lam Tin Tunnel – Northern Footbridge;
· Contract No. NE/2017/01 – Tseung Kwan O – Lam Tin Tunnel –Tseung Kwan O Interchange and Associated Works
· Contract No. NE/2017/02 – Tseung Kwan O – Lam Tin Tunnel – Road P2/D4 and Associated Works.
· Contract No. NE/2017/06 – Tseung Kwan O – Lam Tin Tunnel – Traffic Control and Surveillance System(TCSS) and Associated Works
· Contract No. NE/2017/07 – Cross Bay Link, Tseung Kwan O – Main Bridge and Associated Works.
3.
Environmental monitoring
for the Project was performed in accordance with the EM&A Manual and the
monitoring results were checked and reviewed. Site Inspections/Audits were
conducted once per week. The implementation of the environmental mitigation
measures, Event Action Plans and environmental complaint handling procedures
were also checked.
4. Summary of the non-compliance (exceedance) in the reporting month for the Project is tabulated in Table I.
Table I Non-compliance
(exceedance) Record for the Project
in the Reporting Month
Environmental Monitoring |
No. of
Non-compliance (Exceedance) |
No. of Non-compliance
(Exceedance) due to Construction
Activities of this Project |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
Air Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
12 |
2 |
10 |
0 |
Refer to Appendix K & O |
Marine Water Quality |
37 |
138 |
0 |
0 |
Refer to Appendix K |
Groundwater Level Monitoring (Piezometer Monitoring) |
0 |
N/A1 |
0 |
N/A1 |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
0 |
0 |
0 |
0 |
N/A |
Landfill Gas |
0 |
0 |
0 |
0 |
N/A |
Note:(1) No Limit Level for
Groundwater Level Monitoring (Piezometer Monitoring).
Air Quality Monitoring
5. No Action/Limit Level exceedance for 1-hour TSP monitoring was recorded.
6. No Action/Limit Level exceedance for 24-hour TSP monitoring was recorded.
Construction
Noise Monitoring
7. Ten (10) Action Level exceedances were recorded due to documented project-related complaints received in this reporting month. The Summary of Documented Complaints in Reporting Month is tabulated in Table III.
8. No project-related Limit Level exceedance for construction noise monitoring were recorded in the reporting month.
Water
Quality Monitoring
9.
Groundwater
quality monitoring had been suspended since October 2019 upon the agreement by
EPD. Further details should be
founded at Section 5.1.
10.
All marine water
quality monitoring was conducted as scheduled in the reporting month. There were thirty-seven (37)
Action Level and one-hundred-and-thirty-eight (138) Limit Level exceedances recorded in
Monitoring Stations (M) during marine water quality monitoring. During this reporting month, no sand plume was
observed during the water quality monitoring and site audits, therefore there
is no direct evidence that the recent exceedances were due to the construction
works of the Project. Details of this investigation are presented in Section 5. Daily silt curtain
inspection and weekly diving inspection have been carried out by contractor,
the record, as reviewed by the site auditors, indicated that silt curtains were
found in good conditions.
11. Construction phase daily piezometer monitoring by the Contractor commenced in June 2018. It has switched to monthly basis since 3 October 2018 as the construction activity was 120m away from the piezometer gate. No monitoring was conducted in the reporting month.
Ecological
Monitoring
12. Post-translation coral monitoring survey shall be conducted once every 3 months for a period of 12 months after completion of coral translocation. The post-translocation coral monitoring surveys were completed in November 2017.
Monitoring
on Cultural Heritage
13. Monitoring of impacts on Cultural Heritage at Cha Kwo Ling Tin Hau Temple commenced in May 2017. No Alert, Alarm and Action (AAA) Level exceedance was recorded in the reporting month.
Landscape
and Visual Monitoring and Audit
14. The implementation of landscape and visual mitigation measures was checked during the environmental site inspections. Recommended follow-up actions have been discharged by the Contractor. Details of the audit findings and implementation status are presented in Section 10.
Landfill
Gas Monitoring
15. Monitoring of landfill gases commenced in December 2016 and were carried out by the Contractor at excavation location, Portion III. No Limit Level exceedance was recorded.
Environmental Site Inspection
16. Joint weekly site inspections were conducted by representatives of the Contractor, Engineer and Environmental Team. The representative of the IEC joined the site inspection for NE/2015/01 and NE/2017/07 on 14 April 2021 & NE/2015/02, NE/2017/01, NE/2017/02 and NE/2017/06 on 15 April 2021 respectively. Details of the audit findings and implementation status are presented in Section 10.
Waste
Management
17. Wastes generated from this Project include inert construction and demolition (C&D) materials, non-inert C&D materials and marine sediment. Details of waste management data is presented in Section 11 and Appendix P.
18. Summary of key information in the reporting month is tabulated in Table II
Table II Key
Information in the Reporting Month
Monthly Complaints |
Event Details |
Action Taken |
Status |
|
|
||||
Number |
Nature |
|||
April 2021 |
12 |
Noise |
Details refer to App O |
Draft CIRs submitted / On-going |
March 2021 |
18* |
Noise |
Details refer to App O |
Draft CIRs submitted / On-going |
February 2021 |
3 |
Noise |
Details refer to App O |
Closed/ Draft CIRs submitted/ On-going |
January 2021 |
13 |
Noise / Air |
Details refer to App O |
On-going /Closed |
December 2020 |
13 |
Noise / Operating hours |
Details refer to App O |
Draft CIRs submitted / Closed |
November 2020 |
14 |
Air / Noise |
Details refer to App O |
Closed |
Notifications of any
summons & prosecutions received |
0 |
--- |
N/A |
N/A |
*4 new complaints in
March 2021 was received by Environmental Team in April 2021
19. Summary of complaints received in the reporting month is tabulated in Table III.
Table III Summary of Complaints Details in Reporting
Month
Complaint No. |
Complaint |
Investigation Findings |
Follow-up Action / Mitigation Measure |
Tseung Kwan O Side |
|||
536 |
Suspected
low-frequency noise nuisance at Portion IX (Apr 2021) |
The
complaint is considered as non-project-related as no PME was turned on during
the time of complaint. Details shall be referred to CIR-N136. |
NIL |
537 |
Noise
Nuisance due to Breaking Works (C3- Apr) |
Breaking
works was conducted during the time of complaint. No limit level for noise
monitoring was triggered. The complaint is considered as project-related.
Details shall be referred to CIR-N137. |
NIL as
breaking works ended on late-April. |
538, 539, 545 |
Noise
nuisance on holiday mornings (C2 - Mar) |
No works was
conducted during the time of complaint. The complaint is considered as
non-project-related. Details shall be referred to CIR-N138. |
NIL |
546 |
Noise
nuisance on holiday mornings (C6 - Apr) |
Investigation
undergoing |
|
Lam Tin Side |
|||
534, 535, 540, 541, 542, 543, 544, 547, 548, 549 |
Noise
nuisance during nighttime (C1 - Apr 2021) |
Investigation
undergoing |
20. Summary of key construction work in the reporting month is tabulated in Table IV.
Table IV Summary
Table for Key Construction Work in the Reporting Month
Contract No. |
Project
Title |
Site
Activities (April 2021) |
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works |
Lam Tin Interchange |
1) EHC2 U-Trough 2) Site Formation – Area 1G1, Area 1G2, Area 2 &
Area 5 3) Site Formation – Slope stabilization & Retaining
Wall 4) Aministration Building, West Ventilation Building
& Bridge Construction 5) Stormwater Tank Construction 6) S01_2, EHC1&4 Construction 7) CKLR Underground Utilities 8) Landscape Deck |
Main Tunnel |
9) S02_2 Excavation 10) Main Tunnel Lining Works |
||
TKO Interchange |
11) Bridge Construction 12) East Ventilation Building |
||
NE/2015/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2 and Associated Works |
1)
Site formation works, road and drainage
for Road P2 CH500-CH650 and SR1 2)
Sloping seawall construction 3)
Excavation at CH821 – CH105 Cofferdam 4)
Excavation at CH105 – CH318 Cofferdam 5)
Installation of ELS at CH105 – CH821
Cofferdam 6)
Installation of ELS at cofferdam CH105 –
CH318 7)
Installation of de-watering system at
CH821 – CH105 Cofferdam 8)
Construction of U-trough at CH821 – CH105 9)
Construction of Underpass at CH105 – CH318 10)
Re-construction of watermains DN150/DN200
at Tong Yin Street 11)
Structure works for underpass CH105 –
CH318 12)
Reinstatement of Tong Yin Street 13)
Reinstatement of Chiu Shin Street 14)
Water works PE315 and DN300 15)
Removal of temporary cofferdam 16)
Installation of socketed H-pile at CT01
CH117 – CH336 17)
Construction of seawall coping 18)
Road & drainage works at SR1 footpath
/ cycle track 19)
Excavation of 3rd layer of ELS at CH105 –
CH318 cofferdam 20)
Construction of storm water drain system
for SHH 9101 – 9103 21)
Drainage works at U-trough CH318 –
CH363.50 22)
H-Pile Remedial Works at CH105 – CH318
Cofferdam 23)
Construction of Site Hull Road adjacent to
SR2 CH110 – CH170 |
|
NE/2015/03 |
Tseung Kwan
O – Lam Tin Tunnel – Northern Footbridge |
The construction works under the contract had been
completed in December 2019. The EM&A works were terminated in late April
2020. |
|
NE/2017/01 |
Tseung Kwan
O – Lam Tin Tunnel – Tseung Kwan O Interchange and Associated Works |
1) Construction of Pier 2) Construction of Pier Head Works 3) Construction of Pile Cap 4) Segment Erection Works 5) Installation of Parapet Skin |
|
NE/2017/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2/D4 and Associated Works |
1) Inspection pit excavation and utility diversion
works 2) Construction of drainage and watermain 3) Asphalt Paving 4) Pier, Staircase and Lift Shalt Construction 5) Road Works |
|
NE/2017/06 |
Tseung Kwan
O – Lam Tin Tunnel – Traffic Control and Surveillance System(TCSS) and
Associated Works |
1) System Integration Test 2) Installation works at Admin Building 3) Goods arrival & storage on site |
|
NE/2017/07 |
Cross Bay
Link, Tseung Kwan O – Main Bridge and Associated Works |
1) Predrilling Work at Portion I had completed with 26
out of 35 numbers 2) Precast Shell Installation 3) 1st Stage Concrete for pile caps 4) Precast Pier Installation 5) 2nd Stage Concrete for pile caps 6) Precast Box Girder Installation 7) E&M Work and External Work at Portion V 8) Fabrication of deck segment panels steel 9) Round deck segment assembly 10) Fabrication of arch rib panels steel 11) Round arch rib segment assembly 12) Load-out and Transportation of Steel Main Bridge 13) Load-out, Transportation and Floating-in of Steel
Bridge |
21. The future key environmental issues in the coming month include:
Table V Summary Table for Site
Activities in the next Reporting Period
Contract
No. and Project Title |
Site
Activities (May 2021) |
Key Environmental Issues * |
|
NE/2015/01 - Tseung Kwan O – Lam Tin Tunnel – Main
Tunnel and Associated Works |
Lam Tin Interchange |
1) EHC2 U-Trough 2) Site Formation – Area 1G1, Area 1G2, Area 2 &
Area 5 3) Site Formation – Slope stabilization & Retaining
Wall 4) Administration Building, West Ventilation Building
& Bridge Construction 5) Stormwater Tank Construction 6) S01_2, EHC1&4 Construction 7) CKLR Underground Utilities 8) Landscape Deck |
(A) / (B) / (C) / (D) / (E) / (G) |
Main Tunnel |
9) S02_2 Excavation 10) Main Tunnel Lining Works |
(B) |
|
TKO Interchange |
11) Bridge Construction 12) East Ventilation Building |
(A) / (C) / (D) / (E) / (F) / (I) |
|
NE/2015/02 - Tseung Kwan O – Lam Tin Tunnel – Road
P2 and Associated Works |
1)
Construction of pillar box and ducting
system at Portion IV adjacent to Ocean Shores EVA 2)
Site formation at Road P2 CH500-CH650 and
SR1 3)
Road and drainage works at Road P2 CH500 –
650, slip road SR1 footpath and cycle track, slip road SR2 CH250 – CH350 4)
ELS at underpass P2 CH105 – CH318 5)
4th of excavation at CH105 – CH318
cofferdam 6)
Excavation/ELS at CH821 – CH105 Cofferdam 7)
Installation of socketed H-pile at CT01
CH117 – CH336 8)
Reinstatement of Tong Yin Street 9)
Installation of de-watering system at
CH821 – CH105 10)
Excavation & ELS installation works at
CH821 – CH105 11)
Construction of U-tough at CH821 – CH105 12)
Drainage works at U-trough CH318 –
CH363.50 13)
Pre-bore/ELS works for U-trough CH363.50 –
CH411/U-trough SR2 CH110-CH170 14)
Construction of profile barrier at
U-trough CH318 – CH363.50 15)
Construction of sloping seawall 16)
Removal of temporary cofferdam 17)
Construction of seawall coping 18)
Drainage works at SR1 footpath / cycle
truck 19)
Installation of ELS at cofferdam CH105 –
CH318 20)
Backfilling works for reinstatement of
Tong Yin Street 21)
Construction of U-trough at CH821 – CH 105
Cofferdam 22)
Excavation and re-compaction at S100 CH280
– S200 CH755 and S300 CH405 – CH326 23)
Waterworks – DN300/PE315 24)
RC Structure works for U-trough A-B 25) RC
Structure works for U-trough C |
(A) / (B) / (C) / (D) / (E) / (G) / (I) |
|
NE/2015/03 - Tseung Kwan O – Lam Tin Tunnel –
Northern Footbridge |
The
construction works under the contract had been completed in December 2019.
Materials are being removed from works area. |
N/A |
|
NE/2017/01 – Tseung Kwan O Interchange and
Associated Works |
1) Construction of Pier 2) Construction of Pier Head works 3) Segment erection works 4) Construction of Bridge Decks 5) Installation of Parapet Skin |
(A) / (B) / (E) / (F) / (G) |
|
NE/2017/02 –Tseung Kwan O - Lam Tin Tunnel - Road
P2/D4 and Associated Works |
1) Inspection pit excavation and utility diversion
works 2) Construction of drainage and watermain 3) Asphalt Paving 4) Pier, Staircase and Lift Shalt Construction 5) Road Works |
(A) / (B) / (E) / (F) / (G) |
|
NE/2017/06 – Tseung Kwan O – Lam Tin Tunnel –
Traffic Control and Surveillance System(TCSS) and Associated Works |
1) System Integration Test 2) Goods arrival & storage on site 3) Installation in Admin Building 4) Installation in Tunnel Building |
(E) |
|
NE/2017/07 - Cross Bay Link, Tseung Kwan O – Main
Bridge and Associated Works |
1) Fabrication work for precast pier 2) Preparation for Rolling out for Precast Box Girder 3) Jointing deck segments 4) Dismantle of temporary support towers and loading
out steel main bridge to barge 5) Preparation of temporary support tower 6) Fabrication of Precast Segment and Precast Shell 7) Pre-drilling 8) Bored piling |
(A) / (B) / (D) / (E) / (F) / (G) / (H) / (I) |
Note:
(A)
Watering for dust generation from haul road, stockpiles of dusty
materials, exposed site area, excavation works and rock breaking activities;
(B)
Noisy construction activity such as rock-breaking activities and piling
works;
(C)
Runoff from exposed slope or site area;
(D)
Wastewater and runoff discharge from site;
(E)
Accumulation of silt, mud and sand along U-channels and sedimentation
tanks;
(F)
Set up and implementation of temporary drainage system for the surface
runoff;
(G)
Storage of chemicals/fuel and chemical waste/waste oil on site;
(H)
Accumulation and storage of general and construction waste on site; and
(I)
Marine water quality impact and indirect impact to coral
communities due to marine construction for TKO-LTT reclamation
1.1 Cinotech Consultants Limited (Cinotech) was commissioned by Civil Engineering and Development Department (CEDD) as the Environmental Team (ET) to undertake environmental monitoring and auditing services for the Works Contracts involved in the implementation of Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) project to ensure that the environmental performance of the Works Contracts comply with the requirements specified in the Environmental Permit (EP), Environmental Monitoring & Audit (EM&A) Manual, Environmental Impact Assessment (EIA) Report of the TKO-LTT project and other relevant statutory requirements. This is the 54th Monthly EM&A report summarizing the EM&A works for the Project in April 2021.
1.2 This is the 54th Monthly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period in April 2021.
1.3 The structure of the report is as follows:
Section 1: Introduction – purpose and structure of the report.
Section 2: Contract Information – summarises background and scope of the Contract, site description, project organization and contact details, construction programme, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting month.
Section 3: Air Quality Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, monitoring results and Event / Action Plans.
Section 4: Noise Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, monitoring results and Event / Action Plans.
Section 5: Water Quality Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, monitoring results and Event / Action Plans.
Section 6: Ecological Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations and Action and Limit Levels, monitoring results and Event / Action Plans.
Section 7: Cultural Heritage –summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations and monitoring results.
Section 8: Landscape and Visual Monitoring Requirements – summarises the requirements of landscape and visual monitoring
Section 9: Landfill Gas Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, monitoring results and Limit Levels and Action Plan
Section 10: Environmental Site Inspection – summarises the audit findings of the weekly site inspections undertaken within the reporting month.
Section 11: Waste Management – summarises the waste management data in the reporting month.
Section 12: Environmental Non-conformance – summarises any monitoring exceedance, environmental complaints, environmental summons and successful prosecutions within the reporting month.
Section 13: Future Key Issues – summarises the impact forecast and monitoring schedule for the next three months.
Section 14: Conclusions and Recommendation
2.1 In 2002, Civil Engineering and Development Department (CEDD) commissioned an integrated planning and engineering study under Agreement No. CE 87/2001 (CE) “Further Development of Tseung Kwan O – Feasibility Study” (the “TKO Study”) to formulate a comprehensive plan for further development of TKO New Town. It recommended to further develop TKO to house a total population of 450,000 besides the district’s continuous commercial and industrial developments.
2.2 At present, the Tseung Kwan O Tunnel is the main connection between Tseung Kwan O (TKO) and other areas in the territory. To cope with the anticipated transport need, the TKO Study recommended the provision of Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) (hereinafter referred to as “the Project”) and Cross Bay Link (CBL) to meet the long-term traffic demand between TKO and the external areas. The site layout plan for the Project is shown in Figure 1. CBL was also entrusted with part of the marine viaducts near Tseung Kwan O Interchange since the commencement of the CBL project the December 2018.
2.3 The Environmental Impact Assessment (EIA) Report for the TKO-LTT project was approved under the Environmental Impact Assessment Ordinance (EIAO) in July 2013. The corresponding Environmental Permit (EP) was issued in August 2013 (EP no.: EP-458/2013). Variations to the EP was applied and the latest EP (EP no.: EP-458/2013/C) was issued by the Director of Environmental Protection (DEP) in January 2017.
2.4 The commencement dates of construction of this Project are:
Contract No. NE/2015/01 and Contract No. NE/2015/02: 7 November 2016.
Contract No. NE/2015/03: 29 May 2017.
Contract No. NE/2017/02: 15 March 2018.
Contract No. NE/2017/01: 23 May 2018.
Contract No. NE/2017/06: 09 November 2018.
Contract No. NE/2017/07: 22 February 2021
2.5 Different parties with different levels of involvement in the project organization include:
· Project Proponent – Civil Engineering and Development Department (CEDD)
· The Engineer and the Engineer’s Representative (ER) – AECOM
· Environmental Team (ET) – Cinotech Consultants Limited (Cinotech)
· Independent Environmental Checker (IEC) – AnewR Consulting Limited (AnewR)
2.6 The key contacts of the Project are shown in Table 2.1.
Table 2.1 Key Project
Contacts
Role |
Contact Person |
Phone No. |
Fax No. |
|
CEDD |
Project
Proponent |
Mr. LO Sai Pak, Sunny |
2301 1384 |
2739 0076 |
AECOM |
Engineer’s Representative |
Mr. KY Chan |
3922 9000 |
2759 1698 |
Cinotech |
Environmental
Team |
Dr. HF Chan |
2151 2088 |
3107 1388 |
Mr. KS Lee |
2151 2091 |
|||
AnewR |
Independent
Environmental Checker |
Mr. James Choi |
2618 2836 |
3007 8648 |
2.7 The major site activities undertaken in the reporting month included:
Table 2.2 Summary Table for
Major Site Activities in the Reporting Month
Contract No. |
Project
Title |
Site
Activities (April 2021) |
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works |
Lam Tin Interchange |
1) NE/2015/01 |
Main Tunnel |
2) S02_2 Excavation 3) Main Tunnel Lining Works |
||
TKO Interchange |
4) Bridge Construction 5) East Ventilation Building |
||
NE/2015/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2 and Associated Works |
1)
Site formation works, road and drainage
for Road P2 CH500-CH650 and SR1 2)
Sloping seawall construction 3)
Excavation at CH821 – CH105 Cofferdam 4)
Excavation at CH105 – CH318 Cofferdam 5)
Installation of ELS at CH105 – CH821
Cofferdam 6)
Installation of ELS at cofferdam CH105 –
CH318 7)
Installation of de-watering system at CH821
– CH105 Cofferdam 8)
Construction of U-trough at CH821 – CH105 |