TABLE OF CONTENTS
Environmental
Monitoring Works
Key
Information in the Reporting Month
Key
Construction Work in the reporting month & the next reporting month
Construction
Activities undertaken during the Reporting Month
Status of Environmental Licences,
Notification and Permits
Monitoring
Parameters and Frequency
Monitoring Methodology and QA/QC
Procedure
Monitoring Parameters and Frequency
Sampling Management and Supervision
Post-Translocation Coral Monitoring
Alert, Alarm and Action Levels
Mitigation
Measures for Cultural Heritage
8. LANDSCAPE AND VISUAL IMPACT
REQUIREMENTS
Monitoring Parameters and Frequency
Monitoring Equipment noise mitigation
Implementation Status of
Environmental Mitigation Measures
12. ENVIRONMENTAL NON-CONFORMANCE
Summary of Environmental Complaint
Summary of Environmental Summon and
Successful Prosecution
Key Issues for the Coming Month
14. CONCLUSIONS AND RECOMMENDATIONS
lIST
OF TABLES
Table I Non-compliance (exceedance) Recorded for the Project in the Reporting Month
Table II Key Information in the Reporting Month
Table III Summary Table for Complaint Details in the Reporting Month
Table IV Summary Table for Key Construction Work in the Reporting Month
Table V Summary Table for Site Activities in the next Reporting Period
Table 2.1 Key Project Contacts
Table 2.2 Summary Table for Major Site Activities in the Reporting Month
Table 2.4 Summary of the Status of Environmental Licences, Notification and Permits
Table 3.1 Locations for Air Quality Monitoring
Table 3.2 Air Quality Monitoring Equipment
Table 3.3 Impact Dust Monitoring Parameters, Frequency and Duration
Table 3.4 Major Dust Source during Air Quality Monitoring
Table 4.1 Noise Monitoring Stations
Table 4.2 Noise Monitoring Equipment
Table 4.3 Noise Monitoring Parameters, Frequency and Duration
Table 4.4 Major Noise Source during Noise Monitoring
Table 4.5 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Table 4.7 Baseline Noise Level and Noise Limit Level for Monitoring Stations (Night-time)
Table 5.1 Not Used
Table 5.2 Marine Water Quality Monitoring Stations
Table 5.3 Water Quality Monitoring Equipment
Table 5.4 Water Quality Monitoring Parameters and Frequency
Table 5.5 Methods for Laboratory Analysis for Water Samples
Table 5.6 Not Used
Table
7.1 Cultural Heritage Monitoring
Equipment
Table 7.2 AAA Levels for Monitoring for Cultural Heritage
Table 9.1 Landfill Gas Monitoring Equipment
Table 13.1 Summary Table for Site Activities in the next Reporting Period
lIST OF FIGUREs
Figure
1a Site Portions under Works
Contract No. NE/2015/01 (Lam Tin Side)
Figure
1b Site Portions under Works
Contract No. NE/2015/01 (Tseung Kwan O Side)
Figure 1c Site Portions under Works Contract No. NE/2015/02
Figure
1d Site Portions under Works
Contract No. NE/2015/03
Figure
1e Site Portions under Works
Contract No. NE/2017/01
Figure 1f Site Portions under Works Contract No. NE/2017/01
Figure
1g Site Portions under Works
Contract No. NE/2017/02
Figure
1h Site Portions under Works
Contract No. NE/2017/02
Figure
2 Locations of Air Quality
Monitoring Stations
Figure
3 Locations of Construction
Noise Monitoring Stations
Figure 4 Not Used
Figure
5 Locations of Marine Water
Quality Monitoring Stations
Figure
6 Locations of Landfill Gas
Monitoring
Figure
7 Location of Post-translocation
Coral Monitoring
Figure 8 Location of Monitoring for Cultural Heritage
Figure 9 Not Used
lIST OF APPENDIces
Appendix A
Action
and Limit Levels
Appendix B
Copies of
Calibration Certificates
Appendix C
Weather
Information
Appendix D
Environmental
Monitoring Schedules
Appendix E
1-hour
TSP Monitoring Results and Graphical Presentations
Appendix F
24-hour
TSP Monitoring Results and Graphical Presentations
Appendix G
Noise
Monitoring Results and Graphical Presentations
Appendix H Not Used
Appendix I
Marine
Water Quality Monitoring Results and Graphical Presentations
Appendix J QC/AC
Appendix K
Summary
of Exceedance
Appendix L
Site
Audit Summary
Appendix M
Event and Action Plans
Appendix N
Implementation
Schedule And Recommended Mitigation Measures
Appendix O
Summaries
of Environmental Complaint, Warning, Summon and Notification of Successful
Prosecution
Appendix P
Waste
Generation in the Reporting Month
Appendix Q
Tentative
Construction Programme
Appendix R
Record
of Landfill Gas Monitoring by Contractor
Appendix S Not Used
Appendix T Cultural Heritage Monitoring Results
Appendix U Not Used
Appendix V Surface
Runoff Management Plan
1. This is the 57th Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the “Agreement No. CE 59/2015 (EP) Environmental Team for Tseung Kwan O – Lam Tin Tunnel – Design and Construction” (hereinafter called “the Project”). This report documents the findings of EM&A Works conducted in July 2021.
2. During the reporting month, the following works contracts were undertaken:
· Contract No. NE/2015/01 – Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works;
· Contract No. NE/2015/02 – Tseung Kwan O – Lam Tin Tunnel – Road P2 and Associated Works;
· Contract No. NE/2015/03 – Tseung Kwan O – Lam Tin Tunnel – Northern Footbridge;
· Contract No. NE/2017/01 – Tseung Kwan O – Lam Tin Tunnel –Tseung Kwan O Interchange and Associated Works
· Contract No. NE/2017/02 – Tseung Kwan O – Lam Tin Tunnel – Road P2/D4 and Associated Works.
· Contract No. NE/2017/06 – Tseung Kwan O – Lam Tin Tunnel – Traffic Control and Surveillance System(TCSS) and Associated Works
· Contract No. NE/2017/07 – Cross Bay Link, Tseung Kwan O – Main Bridge and Associated Works.
3.
Environmental
monitoring for the Project was performed in accordance with the EM&A Manual
and the monitoring results were checked and reviewed. Site Inspections/Audits
were conducted once per week. The implementation of the environmental
mitigation measures, Event Action Plans and environmental complaint handling
procedures were also checked.
4. Summary of the non-compliance (exceedance) in the reporting month for the Project is tabulated in Table I.
Table I Non-compliance
(exceedance) Record for the Project
in the Reporting Month
Environmental Monitoring |
No. of
Non-compliance (Exceedance) |
No. of Non-compliance
(Exceedance) due to Construction
Activities of this Project |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
Air Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
0 |
0 |
2 |
0 |
Refer to Appendix K & O |
Marine Water Quality |
39 |
140 |
0 |
0 |
Refer to Appendix K |
Groundwater Level Monitoring (Piezometer Monitoring) |
0 |
N/A1 |
0 |
N/A1 |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
0 |
0 |
0 |
0 |
N/A |
Landfill Gas |
0 |
0 |
0 |
0 |
N/A |
Note:(1) No Limit Level for
Groundwater Level Monitoring (Piezometer Monitoring).
Air Quality Monitoring
5. No
Action/Limit Level exceedance
for 1-hour TSP monitoring was recorded.
6.
No Limit Level and Action Level exceedance for 24-hour TSP monitoring was
recorded.
Construction Noise Monitoring
7. Two
(2) Action Level exceedance was recorded due to documented complaints in the reporting month. The Summary of
Documented Complaints in Reporting Month is tabulated in Table III.
8. No
Limit Level exceedance was
recorded due to monitoring results in this reporting month.
Water Quality Monitoring
9.
Groundwater
quality monitoring had been suspended since October 2019 upon the agreement by
EPD. Further
details should be founded at Section 5.1.
10. All marine water quality monitoring
was conducted as scheduled in the reporting month. There were thirty-nine (39) Action Level and
one-hundred-and-forty (140) Limit Level exceedances recorded in Monitoring
Stations (M) during marine water quality monitoring. During this reporting month, no sand plume was
observed during the water quality monitoring and site audits, therefore there
is no direct evidence that the recent exceedances were due to the construction
works of the Project. Details of this investigation are presented in Section 5. Daily silt curtain
inspection and weekly diving inspection have been carried out by contractor,
the record, as reviewed by the site auditors, indicated that silt curtains were
found in good conditions.
11. Construction phase daily piezometer monitoring by the Contractor commenced in June 2018. It has switched to monthly basis since 3 October 2018 as the construction activity was 120m away from the piezometer gate. No monitoring was conducted in the reporting month.
Ecological
Monitoring
12. Post-translation coral monitoring survey shall be conducted once every 3 months for a period of 12 months after completion of coral translocation. The post-translocation coral monitoring surveys were completed in November 2017.
Monitoring
on Cultural Heritage
13. Monitoring of impacts on Cultural Heritage at Cha Kwo Ling Tin Hau Temple commenced in May 2017. No Alert, Alarm and Action (AAA) Level exceedance was recorded in the reporting month.
Landscape
and Visual Monitoring and Audit
14. The implementation of landscape and visual mitigation measures was checked during the environmental site inspections. Recommended follow-up actions have been discharged by the Contractor. Details of the audit findings and implementation status are presented in Section 10.
Landfill
Gas Monitoring
15. Monitoring of landfill gases commenced in December 2016 and were carried out by the Contractor at excavation location, Portion III. No Limit Level exceedance was recorded.
Environmental Site Inspection
16. Joint weekly site inspections were conducted by representatives of the Contractor, Engineer and Environmental Team. The representative of the IEC joined the site inspection for NE/2015/01 and NE/2017/07 on 28 July 2021 & NE/2015/02, NE/2017/01, NE/2017/02 and NE/2017/06 on 22 July 2021 respectively. Details of the audit findings and implementation status are presented in Section 10.
Waste
Management
17. Wastes generated from this Project include inert construction and demolition (C&D) materials, non-inert C&D materials and marine sediment. Details of waste management data is presented in Section 11 and Appendix P.
18. Summary of key information in the reporting month is tabulated in Table II
Table II Key Information in the
Reporting Month
Monthly Complaints |
Event Details |
Action Taken |
Status |
|
Number |
Nature |
|||
July 2021 |
3 |
Noise / Working Hours |
Details refer to App O |
Draft CIRs submitted / On-going |
June 2021 |
3 |
Light/ Water/ Working Hours |
Details refer to App O |
Draft CIRs submitted / On-going / Closed |
May 2021 |
3 |
Air / Noise |
Details refer to App O |
Closed |
April 2021 |
13*1 |
Noise |
Details refer to App O |
Closed/ Draft CIRs submitted/ On-going |
March 2021 |
18*2 |
Noise |
Details refer to App O |
Closed/Draft CIRs submitted |
February 2021 |
3 |
Noise |
Details refer to App O |
Closed/ Draft CIRs submitted |
January 2021 |
13 |
Noise / Air |
Details refer to App O |
Closed |
December 2020 |
13 |
Noise / Operating hours |
Details refer to App O |
Closed |
Notifications of any
summons & prosecutions received |
0 |
--- |
N/A |
N/A |
*1: 1 complaint at
April 2021 was received at early May 2021.
*2: 4 new complaints
in March 2021 was received by Environmental Team in April 2021.
19. Summary of complaints received in the reporting month is tabulated in Table III.
Table
III Summary of Complaints Details in
Reporting Month
Complaint No. |
Complaint |
Investigation Findings |
Follow-up Action / Mitigation Measure |
Lam Tin Side |
|||
557 |
Noise Nuisance from Construction Works (C1-Jul) |
Investigation undergoing |
|
Tseung Kwan O Side |
|||
558 |
Operation of
Marine Construction Works during Restricted Hours (Jul 2021) |
The
concerned barge was not belong to the TKOLTT project. The complaint is
considered as not non-project-related. |
|
560 |
Construction
Noise Nuisance on Saturday near Ocean Shores (Jul 2021) |
Investigation undergoing. |
20. Summary of key construction work in the reporting month is tabulated in Table IV.
Table IV Summary Table for Key
Construction Work in the Reporting Month
Contract No. |
Project
Title |
Site
Activities (July 2021) |
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works |
Lam Tin Interchange |
1) EHC2 U-Trough 2) Site Formation Area
1G1 & 1G2 & 5 3) Site Formation Area
2 4) Site Formation
Slope Stabilization 5) Site Formation
Retaining Wall 6) Administration
Building 7) West Ventilation
Building 8) Bridge Construction
9) Emergency Stormwater Storage Tank + Stormwater
Pumping Station 10) S01_2, EHC1&4
Construction 11) CKLR Underground
Utilities 12) Landscape Deck 13) LTI Drainage |
Main Tunnel |
14) Main Tunnel Lining
Works 15) S02_2 Excavation
& Lining |
||
TKO Interchange |
16) Bridge Construction 17) East Ventilation
Building |
||
NE/2015/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2 and Associated Works |
1)
Sloping Seawall Construction 2)
Construction of U-trough 3)
Construction of Underpass 4)
Construction of Seawall Coping 5)
Construction of Road P2 and SR2 |
|
NE/2015/03 |
Tseung Kwan
O – Lam Tin Tunnel – Northern Footbridge |
The construction
works under the contract had been completed in December 2019. The EM&A
works were terminated in late April 2020. |
|
NE/2017/01 |
Tseung Kwan
O – Lam Tin Tunnel – Tseung Kwan O Interchange and Associated Works |
1) Construction of Pier 2) Construction of Pier Head Works 3) Construction of Pile Cap 4) Segment Erection Works 5) Installation of Parapet Skin |
|
NE/2017/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2/D4 and Associated Works |
1) Inspection pit excavation and utility diversion works 2) Construction of drainage and watermain 3) Asphalt Paving 4) Pier, Staircase and Lift Shalt Construction 5) Road Works |
|
NE/2017/06 |
Tseung Kwan
O – Lam Tin Tunnel – Traffic Control and Surveillance System(TCSS) and
Associated Works |
1) System Integration
Test 2) Goods arrival &
storage on site 3) Installation in
Admin Building 4) Installation works
inside Tunnel |
|
NE/2017/07 |
Cross Bay
Link, Tseung Kwan O – Main Bridge and Associated Works |
1) Predrilling Work at
Portion I had completed with 31 out of 35 nos. 2) Piling work at
Portion I had completed with 21 out of 35 nos. 3) Precast Shell
Installation with 16 out of 16 nos. had completed at portion II 4) 1st Stage Concrete
for pile caps with 16 out of 16 nos. had completed at Portion II 5) Precast Pier
Installation with 10 out of 10 nos. had completed at portion II 6) 2nd Stage Concrete
for pile caps is 14 out of 14 nos. had completed at Portion II 7) Fabrication of deck
segment panels steel 8) Precast Box Girder
Installation with 14 out of 18 nos. had completed at Portion II Fabrication
of arch rib panels steel 9) E&M Work and
External Work at Portion V Plant Room Building are In-progress SE 4-5 to SE
6-7 10) Fabrication of deck
segment panels (S420M/ML) steel completed 11) 1st, 2nd,
3rd and 4th round deck segment assembly completed 12) Fabrication of arch
rib panels (S690QL) steel completed. 13) 1st, 2nd,
3rd and 4th round arch rib segment assembly |
21. The future key environmental issues in the coming month include:
Table V Summary Table for Site Activities in the next Reporting Period
Contract
No. and Project Title |
Site
Activities (August 2021) |
Key Environmental Issues * |
|
NE/2015/01 - Tseung Kwan O – Lam Tin Tunnel – Main
Tunnel and Associated Works |
Lam Tin Interchange |
1) EHC2 U-Trough 2) Site Formation Area
1G1 & 1G2 & 5 3) Site Formation Area
2 4) Site Formation
Slope Stabilization 5) Site Formation
Retaining Wall 6) Administration
Building 7) West Ventilation
Building 8) Bridge Construction
9) Emergency Stormwater Storage Tank + Stormwater
Pumping Station 10) S01_2, EHC1&4
Construction 11) CKLR Underground
Utilities 12) Landscape Deck 13) LTI Drainage |
(A) / (B) / (C) / (D) / (E) / (G) |
Main Tunnel |
14) S02_2 Excavation
& Lining 15) Main Tunnel Lining
Works |
(B) |
|
TKO Interchange |
16) Bridge Construction 17) East Ventilation
Building |
(A) / (C) / (D) / (E) / (F) / (I) |
|
NE/2015/02 - Tseung Kwan O – Lam Tin Tunnel – Road
P2 and Associated Works |
1)
Sloping Seawall Construction 2)
Construction of U-trough 3)
Construction of Underpass 4)
Construction of Seawall Coping 5)
Construction of Road P2 and SR2 |
(A) / (B) / (C) / (D) / (E) / (G) / (I) |
|
NE/2015/03 - Tseung Kwan O – Lam Tin Tunnel –
Northern Footbridge |
The
construction works under the contract had been completed in December 2019.
Materials are being removed from works area. |
N/A |
|
NE/2017/01 – Tseung Kwan O Interchange and
Associated Works |
1) Construction of Pier 2) Construction of Pier Head works 3) Segment erection works 4) Construction of Bridge Decks 5) Installation of Parapet Skin |
(A) / (B) / (E) / (F) / (G) |
|
NE/2017/02 –Tseung Kwan O - Lam Tin Tunnel - Road
P2/D4 and Associated Works |
1) Inspection pit excavation and utility diversion
works 2) Construction of drainage and watermain 3) Asphalt Paving 4) Pier, Staircase and Lift Shalt Construction 5) Road Works |
(A) / (B) / (E) / (F) / (G) |
|
NE/2017/06 – Tseung Kwan O – Lam Tin Tunnel –
Traffic Control and Surveillance System(TCSS) and Associated Works |
1) Goods arrival &
storage on site 2) Installation in
Admin Building 3) Installation works
inside Tunnel |
(E) |
|
NE/2017/07 - Cross Bay Link, Tseung Kwan O – Main
Bridge and Associated Works |
1) Delivery of precast
box girder 2) Fabrication work
for precast pier 3) Construct cast
in-situ diaphragm 4) Installation of
precast box girder 5) Welding of joint
between main span and side span 6) Welding of joint
between main span and side span 7) Construction of the
Transitions 8) E&N
installation work 9) External work 10) Pre-drilling 11) Bored piling 12) Pile cap
construction |
(A) / (B) / (D) / (E) / (F) / (G) / (H) / (I) |
Note:
(A)
Watering for dust generation from haul road, stockpiles of dusty
materials, exposed site area, excavation works and rock breaking activities;
(B)
Noisy construction activity such as rock-breaking activities and piling
works;
(C)
Runoff from exposed slope or site area;
(D)
Wastewater and runoff discharge from site;
(E)
Accumulation of silt, mud and sand along U-channels and sedimentation
tanks;
(F)
Set up and implementation of temporary drainage system for the surface
runoff;
(G)
Storage of chemicals/fuel and chemical waste/waste oil on site;
(H)
Accumulation and storage of general and construction waste on site; and
(I)
Marine water quality impact and indirect impact to coral
communities due to marine construction for TKO-LTT reclamation
1.1 Cinotech Consultants Limited (Cinotech) was commissioned by Civil Engineering and Development Department (CEDD) as the Environmental Team (ET) to undertake environmental monitoring and auditing services for the Works Contracts involved in the implementation of Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) project to ensure that the environmental performance of the Works Contracts comply with the requirements specified in the Environmental Permit (EP), Environmental Monitoring & Audit (EM&A) Manual, Environmental Impact Assessment (EIA) Report of the TKO-LTT project and other relevant statutory requirements. This is the 57th Monthly EM&A report summarizing the EM&A works for the Project in July 2021.
1.2 This is the 57th Monthly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period in July 2021.
1.3 The structure of the report is as follows:
Section 1: Introduction – purpose and structure of the report.
Section 2: Contract Information – summarises background and scope of the Contract, site description, project organization and contact details, construction programme, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting month.
Section 3: Air Quality Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, monitoring results and Event / Action Plans.
Section 4: Noise Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, monitoring results and Event / Action Plans.
Section 5: Water Quality Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, Action and Limit Levels, monitoring results and Event / Action Plans.
Section 6: Ecological Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations and Action and Limit Levels, monitoring results and Event / Action Plans.
Section 7: Cultural Heritage –summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations and monitoring results.
Section 8: Landscape and Visual Monitoring Requirements – summarises the requirements of landscape and visual monitoring
Section 9: Landfill Gas Monitoring – summarises the monitoring parameters, monitoring programmes, monitoring methodologies, monitoring frequency, monitoring locations, monitoring results and Limit Levels and Action Plan
Section 10: Environmental Site Inspection – summarises the audit findings of the weekly site inspections undertaken within the reporting month.
Section 11: Waste Management – summarises the waste management data in the reporting month.
Section 12: Environmental Non-conformance – summarises any monitoring exceedance, environmental complaints, environmental summons and successful prosecutions within the reporting month.
Section 13: Future Key Issues – summarises the impact forecast and monitoring schedule for the next three months.
Section 14: Conclusions and Recommendation
2.1 In 2002, Civil Engineering and Development Department (CEDD) commissioned an integrated planning and engineering study under Agreement No. CE 87/2001 (CE) “Further Development of Tseung Kwan O – Feasibility Study” (the “TKO Study”) to formulate a comprehensive plan for further development of TKO New Town. It recommended to further develop TKO to house a total population of 450,000 besides the district’s continuous commercial and industrial developments.
2.2 At present, the Tseung Kwan O Tunnel is the main connection between Tseung Kwan O (TKO) and other areas in the territory. To cope with the anticipated transport need, the TKO Study recommended the provision of Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) (hereinafter referred to as “the Project”) and Cross Bay Link (CBL) to meet the long-term traffic demand between TKO and the external areas. The site layout plan for the Project is shown in Figure 1. CBL was also entrusted with part of the marine viaducts near Tseung Kwan O Interchange since the commencement of the CBL project the December 2018.
2.3 The Environmental Impact Assessment (EIA) Report for the TKO-LTT project was approved under the Environmental Impact Assessment Ordinance (EIAO) in July 2013. The corresponding Environmental Permit (EP) was issued in August 2013 (EP no.: EP-458/2013). Variations to the EP was applied and the latest EP (EP no.: EP-458/2013/C) was issued by the Director of Environmental Protection (DEP) in January 2017.
2.4 The commencement dates of construction of this Project are:
Contract No. NE/2015/01 and Contract No. NE/2015/02: 7 November 2016.
Contract No. NE/2015/03: 29 May 2017.
Contract No. NE/2017/02: 15 March 2018.
Contract No. NE/2017/01: 23 May 2018.
Contract No. NE/2017/06: 09 November 2018.
Contract No. NE/2017/07: 22 February 2021
2.5 Different parties with different levels of involvement in the project organization include:
· Project Proponent – Civil Engineering and Development Department (CEDD)
· The Engineer and the Engineer’s Representative (ER) – AECOM
· Environmental Team (ET) – Cinotech Consultants Limited (Cinotech)
· Independent Environmental Checker (IEC) – AnewR Consulting Limited (AnewR)
2.6 The key contacts of the Project are shown in Table 2.1.
Table 2.1 Key Project
Contacts
Role |
Contact Person |
Phone No. |
Fax No. |
|
CEDD |
Project
Proponent |
Mr. LO Sai Pak, Sunny |
2301 1384 |
2739 0076 |
AECOM |
Engineer’s Representative |
Mr. Jackie CW, Ng |
3910 1601 |
3910 1600 |
Cinotech |
Environmental
Team |
Dr. HF Chan |
2151 2088 |
3107 1388 |
Mr. KS Lee |
2151 2091 |
|||
AnewR |
Independent
Environmental Checker |
Mr. James Choi |
2618 2836 |
3007 8648 |
2.7 The major site activities undertaken in the reporting month included:
Table 2.2 Summary Table for Major Site Activities in
the Reporting Month
Contract No. |
Project
Title |
Site
Activities (July 2021) |
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and Associated Works |
Lam Tin Interchange |
1) NE/2015/01 |
Main Tunnel |
2) S02_2 Excavation 3) Main Tunnel Lining Works |
||
TKO Interchange |
4) Bridge Construction 5) East Ventilation Building |