2.1 In 2002, Civil Engineering and Development Department (CEDD) commissioned an integrated planning and engineering study under Agreement No. CE 87/2001 (CE) “Further Development of Tseung Kwan O – Feasibility Study” (the “TKO Study”) to formulate a comprehensive plan for further development of TKO New Town. It recommended to further develop TKO to house a total population of 450,000 besides the district’s continuous commercial and industrial developments.
2.2 At present, the Tseung Kwan O Tunnel is the main connection between Tseung Kwan O (TKO) and other areas in the territory. To cope with the anticipated transport need, the TKO Study recommended the provision of Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) (hereinafter referred to as “the Project”) and Cross Bay Link (CBL) to meet the long-term traffic demand between TKO and the external areas. The site layout plan for the Project is shown in Figure 1.
2.3 The Environmental Impact Assessment (EIA) Report for the TKO-LTT project was approved under the Environmental Impact Assessment Ordinance (EIAO) in July 2013. The corresponding Environmental Permit (EP) was issued in August 2013 (EP no.: EP-458/2013). Variations to the EP was applied and the latest EP (EP no.: EP-458/2013/C) was issued by the Director of Environmental Protection (DEP) in January 2017.
2.4 The commencement dates of construction of this Project is:
Contract No. NE/2015/01 and Contract No. NE/2015/02: 7 November 2016.
Contract No. NE/2015/03: 29 May 2017.
Contract No. NE/2017/02: 15 March 2018.
Contract No. NE/2017/01: 23 April 2018.
Contract No. NE/2017/06: 09 November 2018.
2.5 Different parties with different levels of involvement in the project organization include:
·
Project Proponent – Civil Engineering and Development Department (CEDD)
·
The Engineer and the Engineer’s Representative (ER) –
AECOM
·
Environmental Team (ET) – Cinotech
Consultants Limited (Cinotech)
·
Independent Environmental Checker (IEC) – AnewR Consulting Limited (AnewR)
2.6 The key contacts of the Project are shown in Table 2.1.
Table 2.1 Key
Project Contacts
Role |
Contact
Person |
Phone No. |
Fax No. |
|
CEDD |
Project Proponent |
Mr.
LO Sai Pak, Sunny |
2301 1384 |
2739 0076 |
AECOM |
Engineer’s Representative |
Mr. KY Chan |
3922 9000 |
2759 1698 |
Cinotech |
Environmental Team |
Dr.
HF Chan |
2151
2088 |
3107
1388 |
Mr.
KS Lee |
2151
2091 |
|||
AnewR |
Independent Environmental Checker |
Mr. Adi Lee |
2618 2836 |
3007 8648 |
2.7 The major site activities undertaken in the reporting month included:
Table 2.2 Summary Table for Major Site Activities in the
Reporting Month
Contract No. |
Project
Title |
Site
Activities (December 2018) |
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel – Main Tunnel and
Associated Works |
Lam Tin Interchange |
1)
EHC2
U-Trough 2)
Site
Formation – Area 1G1, Area 1G2, Area 2 , Area 3, Area 4 and Area 5 |
Main Tunnel |
3)
Main
tunnel Excavation |
||
TKO Interchange |
4)
Haul
Road Construction, Site Formation and Slope Works 5)
Steel
Platform for Bridge Construction 6)
Cavern
Excavation |
||
NE/2015/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2 and
Associated Works |
1) Backfilling works 2) Construction of U-trough structure 3) Pre-bore and sheetpile works for 2100 pipe at Portion IV and Portion VII 4) Pre-bore works for decked U-trough 5) Sheet pile works for decked U-trough 6) Drainage works at U-trough CH411-CH500 7) ELS works and construction of P2A RW 8) ELS works for 2100 pipe 9) Construction of desilting opening near retaining wall at P2A Bay 8 at Portion VIII 10) Installation of 2100 storm water pipe at Portion IV / VII 11) King post and de-watering system for proposed U-trough CH318.00 – CH363.50 at Portion V/VI 12) Construction of permanent fence at Ocean Shores 13) CCTV works at covered channel at Portion IV 14) Fabrication of ELS members for proposed ELS system at CH318.00 – CH363.50 15) Removal of damage temporary steel cofferdam 16) Surcharging at surcharge Area 1a 17) Reclamation works at Portion IX 18) Reinstatement of existing seawall at Portion VII 19) Pre-drilling
at P2 CH283 – CH305 |
|
NE/2015/03 |
Tseung Kwan O
– Lam Tin Tunnel – Northern Footbridge |
1) Construction of Main deck 2) Erection of scaffolding for Staircase 1 3) Installation of Lift Car 4) Plate Load Test for the temporary filled area |
|
NE/2017/01 |
Tseung Kwan O
– Lam Tin Tunnel – Tseung Kwan O Interchange and
Associated Works |
1) Repairing Works for Temporary Working Platform 2) Pre-drilling 3) Bored piling 4) Dismantling Works for Temporary Working Platform 5) Construction of Temporary Working Platform |
|
NE/2017/02 |
Tseung Kwan O – Lam Tin Tunnel – Road P2/D4 and
Associated Works |
1) Trial pit 2) Underground utilities detection 3) Temporary traffic arrangement setup 4) Piling Works 5) Construction of Temporary carriageway 6) Pre-bored Socket H-Pile 7) Modification of traffic island 8) Predrilling 9) Construction of Temporary cycle track 10) Construction of drainage and watermain |
2.8 The construction programme showing the inter-relationship with environmental protection/mitigation measures are presented in Table 2.3.
Table 2.3 Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures
Construction
Works |
Major
Environmental Impact |
Control
Measures |
As
mentioned in Table 2.2 |
Noise,
dust impact, water quality and waste generation |
Sufficient watering of the
works site with active dust emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip ticket system
Appropriate
desilting/sedimentation devices provided on site for treatment before
discharge
Use of quiet plant and
well-maintained construction plant
Provide movable noise
barrier |
2.9 A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Summary of the Status of Environmental
Licences, Notification and Permits
Contract No. |
Permit / License No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit (EP) |
||||
N/A |
EP-458/2013/C |
20/1/2017 |
N/A |
Valid |
Notification
pursuant to Air Pollution Control (Construction Dust) Regulation |
||||
NE/2015/01 |
EPD Ref no.: 405305 |
21/07/2016 |
N/A |
Valid |
EPD Ref no.: 405582 |
28/07/2016 |
N/A |
Valid |
|
NE/2015/02 |
EPD Ref no.: 406100 |
12/08/2016 |
N/A |
Valid |
NE/2015/03 |
EPD Ref no.: 416072 |
26/04/2017 |
N/A |
Valid |
NE/2017/02 |
EPD Ref no.: 429867 |
19/01/2018 |
N/A |
Valid |
NE/2017/01 |
EPD Ref no.: 430070 |
25/01/2018 |
N/A |
Valid |
Billing
Account for Construction Waste Disposal |
||||
Account No. 7025431 |
11/07/2016 |
N/A |
Valid |
|
NE/2015/02 |
Account No. 7025654 |
16/08/2016 |
N/A |
Valid |
NE/2015/03 |
Account No. 7026805 |
30/12/2016 |
N/A |
Valid |
NE/2017/02 |
Account No. 7029651 |
22/12/2017 |
N/A |
Valid |
NE/2017/01 |
Account No. 7029994 |
01/02/2018 |
N/A |
Valid |
Vessel Billing Account under construction waste disposal charging
scheme |
||||
NE2015/01 |
Account No. 7027764 |
30/10/2018 |
10/02/2019 |
Valid |
Registration of Chemical Waste Producer |
||||
NE/2015/01 |
Waste Producer No. 5218-290-L2881-02 |
22/08/2016 |
N/A |
Valid |
Waste Producer No. 5213-833-L2532-03 |
22/08/2016 |
N/A |
Valid |
|
NE/2015/02 |
Waste Producer No. 5213-838-C4094-01 |
23/08/2016 |
N/A |
Valid |
NE/2015/03 |
Waste Producer No. 5213-265-W3435-04 |
19/07/2017 |
N/A |
Valid |
NE/2017/02 |
Waste Producer No. 5213-833-Z4004-04 |
01/02/2018 |
N/A |
Valid |
NE/2017/01 |
Waste Producer No. 5213-833-C4262-01 |
12/02/2018 |
N/A |
Valid |
Effluent Discharge License under Water Pollution Control Ordinance |
||||
NE/2015/01 |
WT00025806-2016 |
18/07/2018 |
30/11/2021 |
Valid |
WT00026212-2016 |
16/05/2017 |
30/11/2021 |
Valid |
|
WT00027354-2017 |
22/03/2017 |
31/03/2022 |
Valid |
|
WT00027405-2017 |
22/03/2017 |
31/03/2022 |
Valid |
|
WT-00028495-2017 |
11/08/2017 |
31/08/2022 |
Valid |
|
NE/2015/02 |
WT00026386-2016 |
15/12/2016 |
31/12/2021 |
Valid |
WT00027226-2017 |
23/02/2017 |
28/02/2022 |
Valid |
|
NE/2015/03 |
WT00027295-2017 |
20/03/2017 |
18/04/2019 |
Valid |
WT00027266-2017 |
08/03/2017 |
18/04/2019 |
Valid |
|
NE/2017/01 |
WT00030711-2018 |
11/04/2018 |
30/04/2023 |
Valid |
WT00030716-2018 |
23/05/2018 |
31/05/2023 |
Valid |
|
NE/2017/02 |
WT00030654-2018 |
16/04/2018 |
30/04/2023 |
Valid |
Construction Noise Permit (CNP) |
||||
NE/2015/01 |
GW-RE0418-18 |
23/06/2018 |
22/12/2018 |
Expired
on 22 Dec 2018 |
GW-RE0630-18 |
01/10/2018 |
30/12/2018 |
Expired
on 30 Dec 2018 |
|
GW-RE0598-18 |
05/9/2018 |
04/12/2018 |
Expired
on 04 Dec 2018 |
|
GW-RE0696-18 |
22/10/2018 |
21/12/2018 |
Expired on
21 Dec 2018 |
|
GW-RE0807-18 |
05/12/2018 |
04/03/2019 |
Valid |
|
GW-RE0819-18 |
30/11/2018 |
29/01/2019 |
Valid |
|
GW-RE0808-18 |
30/11/2018 |
28/01/2019 |
Valid |
|
GW-RE0881-18 |
24/12/2018 |
22/06/2019 |
Valid |
|
NE/2015/02 |
GW-RE0384-18 |
02/06/2018 |
01/12/2018 |
Expired on 01 Dec 2018 |
GW-RE0434-18 |
16/06/2018 |
15/01/2019 |
Valid |
|
GW-RE0680-18 |
11/10/2018 |
10/04/2019 |
Valid |
|
GW-RE0732-18 |
31/10/2018 |
29/01/2019 |
Valid |
|
GW-RE0833-18 |
02/12/2018 |
01/06/2019 |
Valid |
|
NE/2017/01 |
GW-RE0744-18 |
03/11/2018 |
02/02/2019 |
Valid |
GW-RE0755-18 |
07/11/2018 |
06/05/2019 |
Valid |
|
Marine
Dumping Permit |
||||
NE/2017/01 |
EP/MD/19-064 |
01/12/2018 |
31/05/2019 |
Valid |
EP/MD/19-065 |
01/12/2018 |
31/12/2018 |
Expired on 31 Dec 2018 |
|
Specified
Process (SP) License |
||||
NE/2015/01 |
L-11-053 |
09/03/2018 |
08/03/2021 |
Valid |
2.10 The EM&A programme requires construction noise monitoring, air quality monitoring, water quality monitoring, environmental site audit, etc. The EM&A requirements for each parameter are described in the following sections, including:
·
All
monitoring parameters;
·
Action
and Limit levels for all environmental parameters;
·
Event
Action Plans;
·
Environmental
mitigation measures, as recommended in the Project EIA Report.
2.11 The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 10 of this report.
2.12 This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the monitoring parameters of the required environmental monitoring works and audit works for the Project in December 2018.