TABLE OF CONTENTS

 

 

EXECUTIVE SUMMARY.. 1

Introduction. 1

Summary of Main Works Undertaken and Key Measures Implemented. 1

Summary of Exceedances, Investigation and Follow-up. 2

Complaint Handling, Prosecution and Public Engagement 3

Reporting Changes. 3

Future Key Issues. 4

1 INTRODUCTION.. 5

Background. 5

Project Organizations. 5

Construction Activities Undertaken During the Reporting Quarter 6

2 ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS. 8

Monitoring Parameters and Monitoring Locations. 8

Environmental Quality Performance Limits (Action and Limit Levels) 8

Monitoring Methodology. 8

Implementation Status of Environmental Mitigation Measures. 8

Site Audit Summary. 8

Status of Waste Management 8

3 MONITORING RESULTS. 9

Weather Conditions. 9

Air Quality. 9

Construction Noise. 9

Ecology. 9

Water Quality. 9

Waste Management 9

Landscape and Visual 10

Influencing Factors on the Monitoring Results. 10

4 NON-COMPLIANCE (EXCEEDANCES) OF THE ENVIRONMENTAL QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS) 11

Summary of Exceedances. 11

Review of the Reasons for and the Implications of Non-compliance. 11

Summary of Complaint, Warning, Notification of Any Summons and Successful Prosecution. 11

5 COMMENTS, CONCLUSIONS AND RECOMMENDATIONS. 12

Review of Monitoring Methodology and the Practicality and Effectiveness of EM&A Programme. 12

Review on Effectiveness of Mitigation Measures. 12

Recommendations. 12

 


 

LIST OF TABLES

Table I Summary Table for Major Site Activities in the Reporting Quarter

Table II Non-compliance Record for the Project in the Reporting Quarter

Table III Summary Table of Complaints, Summons, Prosecutions and Public Engagement Activities in the Reporting Quarter

Table IV Summary Table for Site Activities in the Next Reporting Period

Table 1.1 Key Project Contacts

Table 1.2 Summary Table for Major Site Activities in the Reporting Quarter

Table 3.1 Major Dust Sources during the Monitoring in the Reporting Quarter

Table 3.2 Major Noise Sources during the Monitoring in the Reporting Quarter

Table 3.3 Observations during Ecological Monitoring in the Reporting Quarter

 

 

 

 

lIST OF FIGUREs

Figure 1.1 Layout Plan of the Project Site

Figure 1.2 Project Organisation for Environmental Monitoring and Audit

Figure 2 Locations of Air Quality Monitoring Stations

Figure 3 Locations of Construction Noise Monitoring Stations

Figure 4 Survey Location for Impact Ecological Monitoring

 

 

 

 

LIST OF APPENDICES

Appendix A Construction Programme

Appendix B Monitoring Requirements

Appendix C Action and Limit Levels

Appendix D Environmental Mitigation Implementation Schedule (EMIS)

Appendix E Site Audit Summary

Appendix F Waste Flow Table

Appendix G Graphical Presentations of Air Quality Monitoring Results (1-hour)

Appendix H Graphical Presentations of Air Quality Monitoring Results (24-hour)

Appendix I Graphical Presentations of Noise Monitoring Results

Appendix J Summary of Ecological Monitoring Analysis

Appendix K Summary of Exceedances

Appendix L Summaries of Environmental Complaint, Warning, Summon and Notification of Successful Prosecution